Your comments are encouraged – information can be found at the bottom of this page
The Purpose of this meeting
-
Present the proposed design for Airport Frontage Road Phase 1
-
Provide an update on this project
-
Receive comments on the proposed design
Project Description
This Public Meeting involves improvements for Airport Frontage Road Phase 1. The proposed project will improve access to Lost Island Road by creating a connection to the traffic signal at Airport Circle/Sea Island Parkway intersection.
The project is a two-lane urban section with an 8′ multi-use path on one side. It will also include traffic signal and left turn lane improvements on US 21 (Sea Island Parkway).
The project was originally presented in January/February 2021. Previous information is still available on the meetings page and click Meeting 1 Summary and Recommendation for additional information about the previous meeting.
Project Status
The project requires new Right of Way and the acquisition process is on-going. Construction of the project is anticipated to begin in Spring 2022 and all permits have been obtained.